CE 6713 ESTIMATION
AND QUANTITY SURVEYING, Final year, Department of Civil Engineering, Model Exam
Questions
Answer ALL Questions
PART A – (10 x 2
= 20 Mark )
1.
What
are the various types of building estimate.
2.
What
is prime cost .
3.
Define aqueduct.
4.
What
are the various types of arches.
5.
What
are the data necessary for the preparation of tenders.
6.
Define
rate analysis.
7.
What
is capitalized value.
8.
What
do you understand by standard rent.
9.
What
is the importance of report preparation.
10.
What
are the points to be included in the report.
PART
–B (5x16=80 marks)
11. (a) Prepare the report on the estimate for
the construction of residential building and culvert. (16)
(OR)
(b)Describe the
principles for the preparation ofwater supply scheme. (16)
12. (a) Prepare a detailed estimate of a septic
tank with soak pit and calculate the quantities for the following
(1)earthwork
excavations
(2)P.C.C 1:3:6
(3)B.W in C.M
1:4 IN Septic Tank
(4)B.W in C.M 1:6 with second class brick
in soak pit.
(5)Second class dry brick work in soak
pit
(6)Precast R.C.C work of roof cover slab
(7)Plastering with C.M 1:3 in 12mm thick
(16)
(OR)
(b)Prepare a detailed estimate for
supplying and laying 50mm dia G.I water supply pipe for 200mm length including
jointing trenching up a depth of 90cm. Necessary materials and labour shall be
provided in the estimate.
(16)
13. (a)EPrepare the
detailed estimate of different items of works of a residential building by
centre line method
(1)Length of walls all round the building =
29.40m
(2)Length of walls between kitchen and bed =
3.50m
(3)C/L of wall between kitchen , bed and
living =6.50m.
14. (a)Calculate the
standard rent of a government residential building newly constructed from the
following data:cost of land Rs.10000. cost of construction of the building
Rs.40000. cost of roads with in the compound and fencing Rs.20000. cost of
electric installation including fans 8% of the cost of building. Cost of
electrical installation including fans 10% of the cost of building. Municipal
house tax Rs.400 per annum. Water tax Rs.250 per annum. Property tax Rs.140 per
annum. (16)
(OR)
(b)(i) Explain the purpose of valuation. (08)
(ii)Write
short notes on scrap value, salvage value,marketvalur,book value and sinking
fund (08)
15. (a)Briefly explain the detailed
specifications of road work.
(16)
(OR)
(b)Briefly explain
the following
(i) tender
(ii) contract document
(iii) termination of contract
(iv) overhead cost in analysis
of rates (16)